Tullow suspends gas export

oil-n-gas-bulk-Since yesterday morning due to fault in FPSO Kwame Nkrumah 

GAS export from the Floating Storage and Offloading vessel (FPSO) Kwame Nkrumah was suspended yesterday morning following what Tullow described as an abnormality in compression.

Ms Akua K. Anarfi Twumasi from the External Communications Unit of Tullow Ghana Limited, lead operators of the Jubilee Fields confirmed this to The Finder.

She stated that export of gas is expected to commence in about 36 hours from the time the export was suspended.

As at the time of fining this report yesterday evening, the Volta River Authority (VRA) had not felt the impact of the shutdown because Ghana National Gas Company (GNGC) pipelines had enough gas.

However, Ghana Gas is likely to ask VRA to shutdown this morning because the gas in the pipelines would run out.

Impact on AMERI

The shutdown would render the Africa and Middle East Resources Investment Group’s (AMERI Energy) power plant, which uses only gas, to also shutdown.

This unexpected situation would force Ghana Grid Company (GRIDCo) to shed load and as a result plunge some areas into darkness.

In a related development, Tullow Ghana Limited, lead operators of Ghana’s main oil and gas exploration field, plans to begin a -15-day shutdown of operations at its offshore Jubilee Oil Field from February 3, 2017.

Inter-connection of TEN, Jubilee FPSO

The shutdown is to enable works on between the Tweneboa, Enyenra, Ntomme (TEN) fields and the Jubilee Field for gas exportation from the FPSO Atta Mills.

The interconnection between Ghana’s first and second operating oil and gas fields will enable evacuation and export of additional natural gas from the TEN fields through the 58-km offshore pipeline of Ghana Gas to its onshore Atuabo Gas Processing Plant.  

The shutdown will lead to immediate curtailment of production and export of natural gas from the FPSO Kwame Nkrumah to Atuabo and subsequent curtailment of lean gas from Atuabo to the Aboadze Thermal Enclave, which presently relies on gas from Ghana Gas to generate electricity.

Aboadze has been relying on Atuabo since November 2014 to supply lean gas to generate electricity from its thermal plants and there are fears that the inter-connection exercise could result in “dumsor” within the period.

220mw AMERI to shutdown

The single fired AMERI power plant which relies solely on gas will also shutdown down during the period resulting in the loss of 220megawatts of electricity.

Ghana Gas allays dumsor fears

Corporate Communications Manager of Ghana Gas, Mr. Alfred Ogbamey, is, however, hopeful that rolling power cuts christened ‘dumsor’ will be averted.

According to him, Tullow informed Ghana Gas of the shutdown months ago, as a result of which Ghana Gas has informed its stakeholders and industry partners to plan for the tie-in period.

“All stakeholders and partners along the gas production value chain have been informed and prepped for this. We anticipate that other stakeholders and the VRA, which has long been aware of this and captured it in their 2017 gas forecast, have put in place adequate measures to avert the consequential effect of the TEN inter-connection.”

He said Tullow’s inter-connection is essential to create a corridor from TEN to evacuate and bring additional natural gas on-stream to generate power. It would also enable the TEN fields to be linked to the Jubilee Field and Ghana Gas Offshore Pipeline, he said.

He admits, however, that the nation could face serious challenges within the period. “There’s a snag. VRA is presently unable to offtake their nominated volumes. Tullow and Ghana Gas have been ready to supply Aboadze with 90 million standard cubic feet of gas a day for awhile, but Aboadze’s TAPCO plants are out for maintenance. This has reduced VRA’s lean gas offtake since January.”

Mr. Ogbamey said though Tullow has indicated that the exercise will take 15 days, Ghana Gas has projected 18 days for the exercise to allow for exigencies should they arise.

Ghana Gas to install new gadget 

He said Ghana Gas will take advantage of the curtailment in gas supply to also interconnect its installed second De-ethenizer Overhead Compressor at Atuabo. 

“That will ensure that Atuabo will operate continuously without the need for 4000-hours scheduled maintenance disruptions. When one compressor has to be serviced after 4000 hours of operation, we’d now be able to switch onto the other and carry out works without halting production.”

Oil production began on the TEN fields through the FPSO Atta Mills in August 2016, with gas production projected for February 2017.

Similar to Jubilee, development of TEN includes the use of an FPSO, which will be tied in to subsea infrastructure across the field. 

FPSO Kwame Nkrumah’s perennial challenges

Various challenges have hindered the delivery of a potential 120 million standard cubic feet of gas a day from the FPSO Kwame Nkrumah to the processing plant at Atuabo.

Since gas production commenced, Tullow Ghana has undertaken several unplanned shutdowns of the FPSO Kwame Nkrumah as a result of faulty compressor and other challenges.

Regular supply of gas from the Jubilee fields has been hindered by the continuous failing of the field operator, compressor at the FPSO Kwame Nkrumah.

The compressor used by the oil company works in a similar fashion as pumps. 

It increases the pressure on a fluid and can transport the fluid through a pipe.

 

By Elvis DARKO, Accra

POST TAGS

ABOUT: Nana Kwesi Coomson

[email protected]

An Entrepreneur, Corporate Social Responsibility, Corporate Communications Executive and Philanthropist. Editor-in-Chief of www.233times.com. A Senior Journalist with Ghanaian Chronicle Newspaper. An alumnus of Adisadel College where he read General Arts. His first degree is in Bachelor of Arts - Political Science (major) and History (minor) from the University of Ghana. He holds MSc in Corporate Social Responsibility (CSR) and Energy with Public Relations (PR) from the Robert Gordon University in the United Kingdom. He is a 2018 Mandela Washington Fellow who studied at Clark Atlanta University in USA on the Business and Entrepreneurship track.

View all posts by: Nana Kwesi Coomson  

Leave a Reply

Your email address will not be published. Required fields are marked *

ABOUT 233TIMES

233times is a Ghanaian media house which serves as a major source of exclusive interviews ,music and video downloads, news and more.

233times reports on major events,news covering entertainment, politics, sports, business, technology, etc from within Ghana, Africa and beyond.

We have a platform for the amateur artistes to portray their staggering talents ...more...

CONTACT US

For further enquiries, please contact us via our contact us page link: CONTACT

WE ON SOCIAL MEDIA. FOLLOW US


To advertise with us or make enquiries, please visit 233times.net/advertise or call Selorm (Selorm) | Selorm (Nana Kwesi)